Diamond Polishing Plant

Time performed the role of main contractor on the construction of the development. Why TP as main contractor? The extent and technicality of the mechanical and electrical components, about a third of the project cost each made it expeditious for the client to have Time perform the contract which was done on a “construction management” basis, thereby eliminating substantial overheads and mark-up’s that would normally be associated in employing a conventional main contractor. There were also technical issues such as dust proofing, epoxy flooring, etc. which required expert sub-contractors and suppliers for which Time took responsibility.